Installation of a new drinking water pipeline toward Nelson Mandela, in southwestern Cartagena, is 85% complete, Aguas de Cartagena reported. The project is intended to strengthen supply to several neighborhoods.
A 1.8-kilometer pipeline
The project connects the Mamonal-Gambote bypass with the Nelson Mandela area. It comprises 1.8 kilometers of ductile iron pipe measuring 500 millimeters in diameter and represents an investment of 7.749 billion pesos, according to the utility.
Once operational, the pipeline will increase distribution capacity from the El Cerro treatment plant by 11,000 cubic meters per day. The reported progress does not mean the project is already in service.
Neighborhoods served and road restoration
Besides Nelson Mandela, the utility expects benefits for San Pedro Mártir, El Educador, María Cano, El Silencio, Simón Bolívar, Ciudadela 2000 and Sierrita II, among other areas. It also aims to strengthen distribution to communities supplied from the Colinas tank.
Alongside installation, Aguas de Cartagena is restoring pavement and sidewalks affected by the work. The utility says that work must follow the district Infrastructure Secretariat’s guidelines.
The pipeline is part of a plan to expand and modernize the water network. Its additional capacity is expected after it enters operation, not as an increase already available to households.