Aguas de Cartagena has completed the connection needed to install a new pumping system in Albornoz, along the road to Mamonal. The company expects the project to enter service in late December 2026.
More capacity from El Cerro
The work took place on a 500-millimeter pipeline and forms part of the Booster Albornoz project. It aims to increase drinking water distribution capacity from the El Cerro plant by 10,000 cubic meters per day toward areas currently supplied by the El Bosque plant.
The completed connection is one stage of the project: the increase in capacity is the stated goal for the system, not a result already achieved.
Remaining work and other pipelines
Over the following four weeks, plans include installing hydraulic fittings, building a concrete chamber, mounting the pumps and restoring the work area.
The estimated investment is 3 billion pesos and includes civil, electrical and remote-control works, as well as complementary hydraulic interventions. The company places the project within a broader reinforcement plan that also includes pipelines in Nelson Mandela, Policarpa-Bellavista and Parquiamérica-Tenaris.