Work to curb Magdalena River erosion completed in Santa Lucía, Magangué

Bolívar’s government said it reinforced 1,075 metres of riverbank in Santa Lucía, where erosion had destroyed more than 40 homes.

Two people look at the river from a path with a yellow railing.

Bolívar’s government said on November 17 that work to curb erosion along the Magdalena River had finished in Santa Lucía, a rural district of Magangué. The project covered 1,075 metres of the left bank in an area where the advancing river had destroyed more than 40 homes.

What changed on the riverbank

The work, led by the departmental disaster risk office, included mats to reduce the erosion caused by the current, geobags weighing more than 14 tonnes and a concrete lining. These elements are intended to stabilize the bank.

The project also added a pedestrian path with railings. It provides a walking route along the section where the work took place and complements the bank reinforcement.

Work the community had sought for years

Erosion forced several families to leave their homes. Some residents took turns watching the rising water at night, and the community held protests calling for action. The project gained momentum after Governor Yamil Arana visited the district.

The reinforcement is intended to reduce erosion and flood risk along the treated section, not to eliminate those risks along the entire riverbank.